31 August 2020

Dame Alice Hudson's Blog

This blog captures our historical records of what happened during the school building project. We moved into the new building in September 2020 and Ada Lovelace CofE High School was officially opened by the Bishop of London. You can read more about the official opening here.

31st August…

Continue reading
29 June 2020

Building Progress

29th June 2020

The building project remains on track for handover and occupation by the school in September. Following a recent visit by several members of staff a short video was produced which gives a taste of what the building will look like when completed and showing the latest progress…

Continue reading
20 April 2020

Lockdown Building update

20th April 2020

We are glad to be able to report that Kier Construction have been able to remain at work during the lockdown, in line with government guidance to the construction industry on appropriate Health & Safety measures.

The teams are making very good progress and some classrooms…

Continue reading
21 January 2020

Parents Update on Building

21st January 2020

Current Year 7 & 8 Parents joined us for an update on the Ada Lovelace building progress, as well as news of setting up a PTFA and the exciting opportunities for aesthetic enhancements of the building. Read more below.

Continue reading
18 October 2019

Annexe movement

18th October 2019

Term started with the excitement of moving into The Annexe – a temporary block behind the café area. The Annexe houses all Ada Lovelace tutor groups for morning and afternoon registration, as well as staff offices, but is available to the whole school community for morning…

Continue reading
16 July 2019

Special Visitiors

16th July 2019

We welcomed a special visitor to Ada Lovelace CofE High School earlier this month. The Right Rev’d Peter Broadbent, Bishop of Willesden started his day with Twyford CofE Academies Trust on the William Perkin site where he toured The Annexe – our new temporary block - with our…

Continue reading
13 June 2019

June Progress

13th June 2019

We are very happy to report significant progress has been made this month, both in preparing for the new cohort of Year 7 students on the William Perkin site in September and on the permanent site.

As anyone who has passed the Park View site recently on the North Circular will…

Continue reading
28 March 2019

Archaeological findings on site

28th March 2019

As part of the planning application for the new school building, a stage 1 written scheme of investigation (WSI) was submitted to and approved by Ealing Council in support of the main planning application. As heritage assets of archaeological interest were identified by stage 1,…

Continue reading
8 February 2019

Contractors Progress Report

8th February 2019

An important milestone was reached for Ada Lovelace CofE High School this week. The contractors for the permanent building Kier Construction, took possession of the site on Monday 4th February and have already cleared vegetation and removed the fencing around the old tennis…

Continue reading
24 January 2018

lease on the permanent site

We are delighted to have good news to share with you at the start of the new year.

The ESFA, together with LocatED, finalised the lease on the permanent site for the school, subject to planning permission, just before Christmas.

The southern part of the site, formerly the Barclays Bank…

Continue reading
11 December 2017

Consultation update

The statutory consultation has finished and we have submitted our report to the DfE. A copy of the report can be viewed here.

Continue reading
19 October 2016

New school project update

A number of parents have asked us what they can do to help North Twyford CofE School become a reality. We have therefore prepared a few points for those who would like to take matters further with elected representatives at both local and national level.

Need for a new school

  • Ealing…
Continue reading